(Above) Building C1 swimming pool formwork.

Building C1 – Swimming pool gutter is finished. Swimming pool concrete wall on-going.

Building C2 – The 1st level of tie beams is finished. Formwork removed. Columns for next floor started.

Building C3 – Column work has been added on top of the footing.

(Above) Building C2 with another floor of column work.

(Above-left) Overall area of building C1-C3. (Above-right) More of the footing work for Building C3.